How to track partial construction deliveries without losing the balance

Keep ordered, accepted, rejected and still-open quantities separate.

By ENRO team

Track a partial delivery against its purchase-order line, not as a new unrelated purchase. The remaining balance should explain what is still expected and what has been cancelled.

Work through the quantities

Illustrative order: 500 fittings. First delivery: 300, of which 20 are rejected. Accepted quantity is 280. If rejected fittings are returned and replacement is still expected, the open accepted-quantity balance remains 220. Do not reduce it to 200 simply because 300 arrived at the gate.

On the second delivery, 150 are accepted. Cumulative accepted quantity is 430 and the open balance is 70. If the company cancels those 70 with the supplier's agreement, record a cancellation rather than inventing a final receipt.

Use separate fields

  • PO and line reference, project, specification and unit.
  • Ordered quantity and approved amendments.
  • Each delivery date, delivery-note reference and quantity received.
  • Quantity accepted, awaiting inspection and rejected.
  • Returns, replacements, cancellations and current open balance.
  • Promised delivery date for the balance and follow-up owner.

A truck arriving is not the same as an accepted receipt. If inspection is pending, show it as pending instead of treating the goods as available for use.

Prevent duplicate billing and duplicate orders

Before raising a replacement order, check whether the original supplier still owes the balance. Before paying an invoice, compare its quantities with accepted receipts and previous invoices against the same line.

Review overdue open lines with the site plan. Some balances can be cancelled because the need changed; others are urgent despite a small value. Keep the reason and decision visible. The useful output is not merely a number outstanding, but a clear answer to who will deliver what, by when, and which record confirms it.