What should you check in a subcontractor progress claim?

Review measured work, previous certification and deductions without confusing a claim with approval.

By ENRO team

Review a subcontractor progress claim against the agreed scope, measurement basis and previous claims. A submitted amount is a request for review, not an approved payable amount.

Start with cumulative work

Illustrative example: the reviewer accepts cumulative work worth ₹12 lakh. Previous certified work was ₹9 lakh. The movement in accepted work value is ₹3 lakh before any applicable contract adjustments, tax or deductions.

If the subcontractor claims ₹4 lakh for the period, identify the ₹1 lakh difference by item. It may arise from disputed quantities, a rate difference, an unapproved change or a mistaken previous balance. Do not hide it in a single net adjustment.

Check the supporting record

  • Contract, work package and agreed rates.
  • Claim period and cut-off date.
  • Item-level quantities, units and measurement evidence.
  • Required inspection or acceptance records.
  • Cumulative previously certified values and prior payments.
  • Proposed changes with their actual approval status.
  • Advances, retention or other adjustments only as applicable under the agreement.

There is no universal retention percentage or recovery rule. Follow the actual contract and finance review. This guide does not determine legal entitlement, tax treatment or statutory payment deadlines.

Keep three totals distinct

Claimed, certified and paid amounts answer different questions. A certified amount can still be unpaid. Previous payment may include an advance rather than payment for measured work. Show those categories explicitly when reconciling balances.

Return queries with the exact line reference, evidence needed, owner and response date. Preserve the submitted claim and the reviewed version. At the next period, use the agreed cumulative starting point so the same work is not claimed or deducted twice. A short reconciliation attached to the review is often more useful than another unexplained total on a dashboard.