What is earned value in a construction project?
Earned value expresses completed work using the budget assigned to that work.
By ENRO team
Earned value expresses completed work using the budget assigned to that work.
How to use it in practice
It needs a baseline and a credible method of measuring completion. Planned value represents the budgeted work expected by the cut-off; earned value represents the budgeted value of work completed; actual cost represents the cost incurred. Keep all three on the same scope and date basis.
A simple example
Illustrative example: a package with a ₹10 lakh budget and objectively measured 40 percent completion has ₹4 lakh earned value, regardless of how much cash has been paid.
What to watch for
Earned value is not revenue and not a bank balance. An unreliable completion percentage makes the resulting performance numbers unreliable too.